PROJECT DESCRIPTION

HPA plans to reconstruct the entire west-half of Pier 12 wharf by installing a new steel sheet pile (SSP) wall immediately adjacent (outside) of the existing wharf, leaving the existing wharf in place.  The new dock structure will be designed for an increased surcharge load rating capacity of 1,000 PSF, up from its original design capacity of 500 PSF.  The new SSP wall will also be designed to allow for future maintenance dredging to a grade of 8.6 m below chart datum, however, there is no plans for dredging at this time.

The project will be divided into two separate phases.  Phase 1 will include the southern half of the Pier 12 west-face wall along the Emerald St. Slip and Phase 2 will include the northern half of west-face wall as well as the west-half of north face wall (refer to diagram).

PROJECT SCHEDULE

2017 (Pre-Construction)

Q2- Review structural condition of wharf (completed by GHD)

Q3 -Conduct geo-technical and geo-environmental testing (completed by GHD)

Q3 – Design project, conduct an EED, issue tender documents

Q4 – Award contract

Phase 1 – Construction

2018

Q1 – In Water works (installation of new SSP wall)

Q2 – Out-of Water works (all works behind SSP wall)

Phase 2 – Construction

2018

Q3-Q4 – Prepare tender documents and award contract

2019

Q1-Q2 – In Water works (installation of new SSP wall)

Q2-Q3 – Out-of Water works (all works behind SSP wall)

 

MORE INFORMATION:

Pier 12 West – Mitigation Measures

Community

We work with community partners to support prosperity and quality of life in Hamilton.

Learn More

News Feed

Read all that’s happening at the Hamilton Port Authority

Learn More

Ships in Port

See the vessels coming and going from Hamilton Harbour.

Learn More